Re: CN52N , Project Component Overview

$
0
0

hi all and thanks for response.

 

My problem is that I want to report on what/which componetns we have consumed in the project without going via a cost report.  It often happends that even the components is picked somboddy delete the component in the builder.  It's in the report (CN52N) as deleted, it's in the cost report as consumed, but actually the project did not need it.  Maybe running reservation report would help, but to me it look silly when the status say DLT REL in the CN52N when it's either deleted or not deleted.

 

Maybe CN52N os ot to be used for project which has been CLSD?